Actively supporting Bangladesh's major infrastructure developments

🛣️
Road Infrastructure

Sylhet-Tamabil Highway Expansion

Sylhet RHD 2023-02-15 → 2026-08-31 ৳280 Crore
30%
Completed

Road widening and improvement project providing motor graders, compactors, and asphalt equipment along the Sylhet-Tamabil corridor.

Equipment in use: Motor Grader Dynapac Compactor Dump Trucks
Port Development

Chittagong Port Container Terminal

Chittagong CPA 2022-06-01 → 2026-03-31 ৳620 Crore
40%
Completed

Earthmoving and heavy construction support for the new container terminal expansion at Chittagong Port.

Equipment in use: Bulldozer Fleet Wheel Loaders Dump Trucks
🚇
Urban Transit

Dhaka Metro Rail Extension Phase 2

Dhaka DMTCL 2022-01-10 → 2025-12-31 ৳1200 Crore
55%
Completed

Supply and operation of specialized construction equipment for underground and elevated metro rail construction in Dhaka city.

Equipment in use: Bauer Piling Rig Volvo Excavator XCMG Crane
🏭
Industrial Zone

BSMIC Infrastructure Development

Mirsharai BEZA 2021-09-01 → 2024-12-31 ৳430 Crore
60%
Completed

Infrastructure development support for the largest industrial economic zone in Bangladesh including road construction and utility installation.

Equipment in use: Grader Compactor Excavator Fleet
🚆
Infrastructure

Padma Bridge Rail Link Project

Munshiganj Bangladesh Railway 2021-03-15 → 2025-06-30 ৳850 Crore
75%
Completed

Providing heavy equipment fleet including excavators, dump trucks, and cranes for the rail link construction connecting Dhaka to Jessore via Padma Bridge.

Equipment in use: CAT 336 Excavator Komatsu Dump Truck Liebherr Crane
🌊
Water Resources

Jamuna River Flood Protection

Sirajganj BWDB 2022-11-01 → 2024-10-31 ৳195 Crore
85%
Completed

Providing excavators and dredging support equipment for the embankment and flood protection works along the Jamuna river.

Equipment in use: Long Reach Excavator Dump Trucks Compactor
🚧
Aviation

Cox's Bazar Airport Expansion

Cox's Bazar CAAB 2020-01-15 → 2023-12-31 ৳340 Crore
100%
Completed

Runway expansion and terminal construction support for Cox's Bazar International Airport.

Equipment in use: Excavators Bulldozers Cranes
🚧
Aviation

Hazrat Shahjalal Int'l Airport T3

Dhaka CAAB 2019-03-01 → 2023-10-15 ৳780 Crore
100%
Completed

Terminal 3 construction and modernization of Shahjalal International Airport in Dhaka.

Equipment in use: Tower Cranes Piling Rigs Heavy Haulers